Background

In early 2014, the new Southmead hospital redevelopment is due to be opened to the public. The developers provided funding to improve the capacity of the ring road approach to Filton Roundabout to address the additional congestion generated by the hospital development. Even with this planned improvement, the roundabout will still be heavily congested due to the volume of traffic in the area.

Purpose of Scheme
The council would like to increase the capacity of this roundabout further than those improvements that can be delivered by the hospital funding alone. The hospital funded works that involve widening into the southern footway would become phase 1 of a bigger junction improvement.
 
Proposed scheme
The Hospital funded phase 1 widening described above will be extended further by a phase 2 scheme. This will be achieved by widening into the northern footway.
 
Please review the Statement of reasons for the scheme and associated drawings that describe the proposals.
The phase 1 proposals funded by the hospital development have already been consulted upon and this consultation relates to the extended phase 2 proposals only. If you would like to comment on the phase 2 proposals please respond to this consultation by replying before the closing date of 17 June 2013

This consultation has now closed, feedback on the consultation is now available.

Timeline

  • Opened
    20 May 2013 at 00:00
  • Closed
    17 Jun 2013 at 23:59
  • Response Published
    25 Feb 2014

Summary of Results

  • Consultation feedback
    This document describes the results of the consultation and what the next steps are.

Documents

  • Statement of reasons with future A38 works
    This describes the reasons for the scheme, the proposed works and briefly outlines future consultations for the A38 Corridor.
  • Plan of the proposed works
    This plan shows the proposed Ring road widening phase 2 works for this consultation shaded in blue. This plan also shows the phase 1 works shaded in green which have been previously consulted on and are due to start construction 10 June 2013
  • A38 Corridor future improvements
    A plan showing the extent of the A38 Corridor improvements due to be consulted on in the near future.

Details

Consultation Topic
  • Local highways and transportation projects
Geographical area
  • Filton
Marking a consultation as relevant to a particular audience indicates that it may be of special relevance to people within that group. It doesn't, however, mean that other groups wont find the consultation of interest - we welcome responses from everybody.
For example, education issues may be of particular interest to Parents & Guardians, and so will be shown to people searching the system for parenting issues, but the views of others (eg: Business, Faith Groups) are also relevant.
Target Audience
  • Councillors / MPs / MEPs
  • Expert stakeholders
  • General public
  • Police
  • Town and Parish Councils
Contact Details

If you have any questions or would like to make any comments, please respond to:

Transportation Services
South Gloucestershire Council
PO Box 2081
Thornbury
BS35 9BP

Tel: 01454 868004
Fax: 01454 863757
email: transportservices@southglos.gov.uk